Kitchen Remodel Timeline: How Long Does It Take in DFW?
One of the most common questions we hear: 'How long will my kitchen remodel take?' Here's an honest, phase-by-phase timeline based on typical DFW projects.
Last updated: March 2026
A standard kitchen remodel in DFW takes 8-12 weeks for construction, with an additional 3-4 weeks for design and permitting. If custom cabinets are ordered, add 12-16 weeks for manufacturing — making the total timeline 16-20 weeks.
Phase 1: Design & Planning (2-4 weeks) — Consultation, measurements, design development, material selections, and finalizing the scope of work.
Phase 2: Permits & Ordering (1-3 weeks) — Building permit applications with the City of Richardson, ordering materials and cabinets, and scheduling subcontractors.
Phase 3: Demolition (2-5 days) — Removing old cabinets, countertops, flooring, and fixtures. Protecting adjacent rooms from dust and debris.
Phase 4: Rough Work (1-2 weeks) — Electrical, plumbing, and any structural modifications. This phase requires inspections before moving forward.
Phase 5: Installation (3-5 weeks) — Cabinet installation, countertop template and installation, flooring, backsplash, painting, and appliance hookup.
Phase 6: Finishing & Punch List (3-5 days) — Hardware installation, final paint touch-ups, cleaning, and a detailed walkthrough to verify every detail.
Typical Timelines
| Project Type | Timeline |
|---|---|
| Cosmetic Refresh | 4-6 weeks total |
| Standard Remodel (stock cabinets) | 10-14 weeks total |
| Standard Remodel (custom cabinets) | 16-20 weeks total |
| Major Renovation (layout changes) | 14-20 weeks total |
| Full Gut Renovation | 16-24 weeks total |
Prices reflect 2026 DFW market rates. Actual costs vary by project scope and site conditions.